← Back to TranscriptAgent TranscriptAgent
← All mining companies

Atomic EagleASX:AEU

Uranium developer, with a project stated to be in southern Zambia.

NoneZambia — as stated on the recordings

developer uranium NoneZambia
Feb 2026 → May 2026Covered
10 of 10Topics on record
6Figures tracked over time
1 executiveNamed on the record
Generate Claims & Checks What management and commentators said, and what still needs independent verification 5 interviews with the company
Stage
Developer
Primary commodity
Uranium
Jurisdiction
southern Zambia
Deposit
heap leach operation with low strip
Latest appearance
31 May 2026
On record
5 interviews · 92 statements · 1 executive

At a glance

What the record holds today. Every card names where it came from — a management representation is not an established fact, and the page never blurs the two.

What is in the ground
29 million pounds at Dwi East
Management-stated Phil Hoskins May 2026
Grade
220 through to 350 to 400 ppm over entire region
Management-stated Phil Hoskins Mar 2026
Money on hand
$9 million in the bank by end of year
Stated capital need: 700,000 dollars of drilling for 24% resource increase
Management-stated Phil Hoskins May 2026
What happens next
30,000 m exploration program underway, largest program the project has seen in almost 20 years
Management-stated Phil Hoskins May 2026
The main open question
The company trades on junior exchanges (OTCQB and ASX), operates in Zambia with permitting still pending, and faces a $350 million capex requirement for an 8 million ton per annum plant—a scale and cost not yet de-risked by feasibility…
Weighed from the statements below, not our opinion of the company.
Our reading

How the stated figures have moved

The same figure, as management put it on the earliest and the latest recording we hold. A difference may be a genuine update, a different measure of the same thing (total against indicated), or a mis-heard number — both quotes are here, and both recordings are one click away.

Study due ● Moved later 2025 → 2027 as stated 3 statements on record
22 Feb 2026
early March 2025
“over the next couple of weeks I think in early March we'll come out with the resource upgrade”
31 May 2026
2027 will be about met test work and updating studies
“2027 will be about met test work and and updating studies.”
Recovery ● Broadly unchanged 3 statements on record
22 Feb 2026
plus 90%
“the recoveries are plus 90% um in pretty quick time”
18 May 2026
greater than 90%
“achieving high recoveries greater than 90% with low acid consumption”
Grade ● Lower 3 statements on record
22 Feb 2026
344 ppm
“the Mutanga project, 47 million pounds at 344 ppm”
26 Mar 2026
309 ppm
“our principal asset being the Mantunga uranium project in Zambia where we recently increased the resource 24% to 58.8 million pounds at 309 ppm.”
Resource size 47 million9.7 million ≠ Different basis One statement qualifies the figure and the other does not (resource) 11 statements on record
22 Feb 2026
47 million pounds
“the 47 million pounds um is yes, sitting on mining licenses”
31 May 2026
9.7 million pound resource at Chisabuka over an 800 by 600 m meter zone
“first drilling of the year was at Chisabuka where last year we had defined a 9.7 million pound resource uh and that's only over an 800 by 600 m meter zone.”
Burn rate ≠ Different measure Stated in time, then in money — not the same quantity 2 statements on record
22 Feb 2026
just short of half by end of calendar year
“I'd say by the end of this calendar year we'll have uh just short of half of that”
03 Apr 2026
700,000 dollars of drilling for 24% resource increase
“To do that with 700,000 dollars of drilling.”
Capex 20%350 million ≠ Different measure Stated in percent, then in money — not the same quantity 2 statements on record
26 Mar 2026
Bannerman capex is 20% higher for plant throughput more than twice as high
“Banaman's capex is 20% higher for a plant throughput that's more than twice as high uh twice as large.”
03 Apr 2026
350 million dollars for 8 million ton per annum plant
“when we look at uh at an 8 million ton per annum plant at a cost of 350 million dollars”

Management view vs outside view

Management interviews are promotional by nature; the outside view is the counterweight. Both are quoted from the recordings, not added by us.

What management spends its time on

Counted from Atomic Eagle's own claims across 5 interviews — most-covered theme first.

What outside voices pick up on

No independent commentary on record yet — so far the page carries only the company's own voice.

Bull · Bear · Watch next

Weighed from the statements on this page — management's pitch and the outside view. Not financial advice, and not our opinion of the company.

▲ Bull case

Management says the company has 58.8 million pounds at Chisabuka with another 40-100 million in exploration targets, plus a second deposit of 29 million pounds at Dwi East—all with simple heap leach processing at >90% recovery and low acid…

What it rests on
Evidence: 3 moments from 2 interviews
Read the full case

Management says the company has 58.8 million pounds at Chisabuka with another 40-100 million in exploration targets, plus a second deposit of 29 million pounds at Dwi East—all with simple heap leach processing at >90% recovery and low acid costs around 20 kg/ton. Founded by veterans of Boss Energy and Lotus Resources, the team has drilled 50,000 meters this year on $19 million cash, achieving a 24% resource increase for $700,000 in drilling costs, with environmental approvals expected by mid-2026 and feasibility study updates due in 2027.

▼ Bear case

The company trades on junior exchanges (OTCQB and ASX), operates in Zambia with permitting still pending, and faces a $350 million capex requirement for an 8 million ton per annum plant—a scale and cost not yet de-risked by feasibility…

What it rests on
Evidence: 2 moments from 2 interviews
Read the full case

The company trades on junior exchanges (OTCQB and ASX), operates in Zambia with permitting still pending, and faces a $350 million capex requirement for an 8 million ton per annum plant—a scale and cost not yet de-risked by feasibility study. No independent engineering review or outside validation is on record; management's exploration targets of 40-100 million pounds remain undrilled assumptions, and the path to first production "towards the end of this decade" leaves significant execution risk ahead.

◆ Watch next

Environmental and resettlement approvals expected mid-2026 (fact 20).

What it rests on
Evidence: 2 moments from 1 interview
Read the full case

Environmental and resettlement approvals expected mid-2026 (fact 20). Mineral resource update and drill program conclusions by end of 2026 (facts 16, 26). Feasibility study update in 2027 with metallurgical test work (facts 6, 30). First production timeline—late decade—depends on permit progression and financing closure.

Each moment links to the exact point in the source recording. The cases are drawn from the transcripts, weighed as written — they are not a rating, a target or a recommendation.

Project 48 statements

The deposit 29

Key takeaway. Management describes the Atomic Eagle deposit as a uranium project within the Karu sandstone basin amenable to shallow heap leach mining with low strip ratios (Apr, Mar 2026).

Read the full summary

The company reports a current resource of 58.8 million pounds at 309 ppm (multiple months), which grew from 47 million pounds at the time of acquisition (Mar 2026). In addition, management points to significant exploration upside, estimating between 40 and 100 million pounds of potential beyond the current resource, putting total possible size between 100 and 150 million pounds (May 2026). They note that the Chisabuka satellite deposit, where a 9.7 million pound resource sits over an 800 by 600 m zone, has a lot of further upside, and that the company has probably only touched 25–30% of the Chisibuka region so far (Apr 2026).

What was actually said
exploration upside
between 40 and 100 million pounds in addition to resource, putting total size between 100 and 150 million pounds
“our over overall expiration target was between 40 and 100 million pounds in addition to our resource. So that puts the size of the prize somewhere between 100 and 150 million pounds according to our geologists.”
Phil Hoskins· 31 May 2026·
exploration upside
anomalies at Manga North between 3 and 5 km long
“there's several anomalies between 3 and 5 km long.”
Phil Hoskins· 31 May 2026·
exploration upside
another five odd million pounds potential at Chisabuka from a 600 by 300 m high grade zone
“I think it's a 600 by 300 m high higher grade zone that's been defined uh there and you know rough rule of thumb if you look at the size of those things could be another five five odd million pounds”
Phil Hoskins· 31 May 2026·
Show the other 26 statements
exploration upside
1100 km of tenure
“there's so much opportunity there given 1100 km of of tenure.”
Phil Hoskins· 31 May 2026·
resource size
29 million pounds at Dwi East
“we've already got 29 million there.”
Phil Hoskins· 31 May 2026·
resource size
58 million pounds
“24% increase in the resource from 47 million to 58.”
Phil Hoskins· 31 May 2026·
resource size
9.7 million pound resource at Chisabuka over an 800 by 600 m meter zone
“first drilling of the year was at Chisabuka where last year we had defined a 9.7 million pound resource uh and that's only over an 800 by 600 m meter zone.”
Phil Hoskins· 31 May 2026·
exploration upside
40 to 100 million pounds in addition to 58.8 million
“exploration target uh that we released in December was 40 to100 million”
Phil Hoskins· 18 May 2026·
reserve size
4 million at 359 ppm
“The measured and indicated component of that is 4 million at 359 ppm”
Phil Hoskins· 18 May 2026·
resource size
58.8 million at 309 ppm
“the resource is 58.8 million at 309 ppm”
Phil Hoskins· 18 May 2026·
resource size
116 million pounds at 1300 ppm in Niger
“It's 116 million pounds at 1300 ppm”
Phil Hoskins· 18 May 2026·
deposit type
heap leach operation with low strip
“low asset consumption um heap leach operation with low strip um is very much like what uh what Bannerman is”
Phil Hoskins· 03 Apr 2026·
exploration upside
probably only touched 25, 30% of Chisibuka region
“we've probably only touched 25, 30% of of that whole region.”
Phil Hoskins· 03 Apr 2026·
exploration upside
over 500 million pounds within these known basins historically
“quite a prospective region and basin for uranium resources with over 500 million pounds within these known basins historically.”
Phil Hoskins· 03 Apr 2026·
resource size
eight targets within Mutanga North
“There's eight targets within an area called Mutanga North um that exhibit all of those characteristics”
Phil Hoskins· 03 Apr 2026·
resource size
58.8 million pounds
“24% increase in the overall resource from 47.4 million pounds to 58.8 million pounds.”
Phil Hoskins· 03 Apr 2026·
resource size
two targets called Namakande 1 and Namakande 2 near Chisibuka
“down near Chisibuka, there's two targets called Namakande 1 and Namakande 2 that are exactly the same.”
Phil Hoskins· 03 Apr 2026·
deposit type
shallow heap leach, Karu sandstone basin
“We are all within this Karu sandstone basin which which does host um over 500 million pounds of resources in southern Africa.”
Phil Hoskins· 26 Mar 2026·
exploration upside
could find another Dibwi East or two Dibwi Easts in exploration this year
“We could find another dibwi east or two dwi easts um in some of the exploration this year.”
Phil Hoskins· 26 Mar 2026·
exploration upside
11 million pounds added, majority from Chisabuka satellite deposit which has a lot of upside
“the 11 million pounds we've added uh the majority of that's come from a a satellite deposit called Chisabuka which has a lot of upside as well.”
Phil Hoskins· 26 Mar 2026·
grade
220 through to 350 to 400 ppm over entire region
“grades anywhere from sort of 220 through to sort of 350 to 400 ppm um over this entire region.”
Phil Hoskins· 26 Mar 2026·
grade
309 ppm
“our principal asset being the Mantunga uranium project in Zambia where we recently increased the resource 24% to 58.8 million pounds at 309 ppm.”
Phil Hoskins· 26 Mar 2026·
resource size
47 million pound resource at time of acquisition
“Montunga at the time was a 47 million pound resource”
Phil Hoskins· 26 Mar 2026·
resource size
58.8 million pounds
“our principal asset being the Mantunga uranium project in Zambia where we recently increased the resource 24% to 58.8 million pounds at 309 ppm.”
Phil Hoskins· 26 Mar 2026·
deposit type
heap leach operation
“it it is a a heap leach operation”
Phil Hoskins· 22 Feb 2026·
exploration upside
between 40 and 100 million pounds
“the exploration target that we released in December last year, uh which was um between 40 and 100 million pounds”
Phil Hoskins· 22 Feb 2026·
exploration upside
satellite deposits in addition to 47 million pounds
“we know that we can fold those those other satellite deposits in as well”
Phil Hoskins· 22 Feb 2026·
grade
344 ppm
“the Mutanga project, 47 million pounds at 344 ppm”
Phil Hoskins· 22 Feb 2026·
resource size
47 million pounds
“the 47 million pounds um is yes, sitting on mining licenses”
Phil Hoskins· 22 Feb 2026·

Jurisdiction 10

Key takeaway. Atomic Eagle operates in Zambia and Niger, management says.

Read the full summary

In southern Zambia, the company reports it holds mining licenses and has lodged environmental approvals and a relocation action plan (March 2026); by April 2026 it added that it is operating under ASX and JORC compliance requirements. As of May 2026, management expects environmental and social impact assessment approvals and the relocation action plan approval in Zambia over the next month or so, while in Niger environmental approvals and the resettlement action plan are also expected around mid-2026.

What was actually said
permit status
environment and social impact assessment approvals and relocation action plan approvals expected over the next month or so
“those approvals are on track and our expectation is over the next month or so that we should have those um approvals in place.”
Phil Hoskins· 31 May 2026·
country
Niger
“we have a worldclass asset um in Nger that was expropriated from GOIX in 2024”
Phil Hoskins· 18 May 2026·
country
Zambia
“our Mantunga uranium project in southern Zambia”
Phil Hoskins· 18 May 2026·
Show the other 7 statements
permit status
environmental approvals and resettlement action plan expected mid 2026
“our expectation is in the coming months around mid 2026 we should be in receipt of the environmental approvals”
Phil Hoskins· 18 May 2026·
country
Zambia
“So, you're in Zambia, the third best mining jurisdiction the Fraser Institute says in Africa.”
Phil Hoskins· 03 Apr 2026·
permit status
operating with ASX and JORC compliance requirements
“the ASX required an independent review from an engineer to sign off that the inputs used by Goviex were reasonable.”
Phil Hoskins· 03 Apr 2026·
country
Zambia
“our principal asset being the Mantunga uranium project in Zambia”
Phil Hoskins· 26 Mar 2026·
permit status
mining licenses held, environmental approvals and relocation action plan lodged
“these uh resources sit on mining licenses um we we do uh benefit from the fact that environmental approvals and relocation action plan were all lodged through 2025”
Phil Hoskins· 26 Mar 2026·
country
Zambia
“the Mutanga uh uranium project in Zambia”
Phil Hoskins· 22 Feb 2026·
region
southern Zambia
“tenure in southern Zambia”
Phil Hoskins· 22 Feb 2026·

Technical risk 9

Key takeaway. Management describes the project's metallurgy as a very simple heap leach operation with high recoveries and low acid consumption.

Read the full summary

The company reports recovery rates of greater than 90% (May 2026, Feb 2026) and plus 90% on average (Mar 2026). Key assumptions include low acid consumption around 20 kg per ton (May 2026), averaging around 20 kg per ton (Feb 2026), and 21-day average leach kinetics (Mar 2026). Regarding technical risk, the company stated in March 2026 that while grades vary from 220 to 400 ppm, recovery and acid consumption are mostly similar across that range.

What was actually said
metallurgy
simple heap leach processing, high recoveries, low acid consumption, low strip open pit mining
“the very simple uh heap leach processing, high recoveries, low acid consumption, uh very simple um low strip open pit mining.”
Phil Hoskins· 31 May 2026·
key assumption
low acid consumption around 20 kg per ton
“low acid consumption around 20 kg per ton and that's a real driver of operating costs”
Phil Hoskins· 18 May 2026·
recovery rate
greater than 90%
“achieving high recoveries greater than 90% with low acid consumption”
Phil Hoskins· 18 May 2026·
Show the other 6 statements
key assumption
21 day average leech kinetics
“21day average leech kinetics and an extremely low acid consumption of 20 kilograms per ton of ore treated.”
Phil Hoskins· 26 Mar 2026·
metallurgy
very simple heap leach operation
“it is a very simple heap leach operation.”
Phil Hoskins· 26 Mar 2026·
recovery rate
plus 90% on average
“Excellent recoveries plus 90% on average.”
Phil Hoskins· 26 Mar 2026·
stated risk
variability in grades from 220 to 400 ppm, recovery and acid consumption mostly similar
“grades anywhere from sort of 220 through to sort of 350 to 400 ppm um over this entire region. Um the recoveries have been um mostly very similar um and acid consumption's pretty similar as well.”
Phil Hoskins· 26 Mar 2026·
key assumption
acid consumption averaging around 20 kg per ton
“the acid consumption is incredibly low, averaging around 20 kg um of acid per ton”
Phil Hoskins· 22 Feb 2026·
recovery rate
plus 90%
“the recoveries are plus 90% um in pretty quick time”
Phil Hoskins· 22 Feb 2026·

Economics 18 statements

Economics 10

Key takeaway. Atomic Eagle management has described the project economics using various metrics across multiple statements.

Read the full summary

In April 2026, the company cited a capex of US$350 million for an 8-million-ton-per-annum plant, with an operating cost of 3.5 million tons per annum producing roughly 2.2 million pounds per annum; they added that economics require optimization at today's uranium price. Earlier, in March and February 2026, management assumed a uranium price of US$90 per pound, and mentioned a potential scenario of 3.9 million pounds per annum over 12 years. The company also noted that Bannerman's capex is 20% higher for a plant with more than twice the throughput. These figures span different dates and assumptions, and not all metrics are directly comparable.

What was actually said
operating cost
2.2 million pounds per annum
“a 12-year heap leach operation at 2.2 million pounds per annum”
Phil Hoskins· 18 May 2026·
capex
350 million dollars for 8 million ton per annum plant
“when we look at uh at an 8 million ton per annum plant at a cost of 350 million dollars”
Phil Hoskins· 03 Apr 2026·
operating cost
about US 40 dollars per meter for exploration drilling
“the sort of drilling we're doing is about US 40 dollars all in.”
Phil Hoskins· 03 Apr 2026·
Show the other 7 statements
operating cost
3.5 million ton per annum plant producing roughly 2.2 million pounds per annum
“the 3.5 million ton per annum plant, uh which was producing roughly 2.2 million pounds per annum”
Phil Hoskins· 03 Apr 2026·
price assumption
economics require optimization at today's uranium price
“What it has taught us is where we need to optimize the project to make it economic at today's uranium price.”
Phil Hoskins· 03 Apr 2026·
capex
Bannerman capex is 20% higher for plant throughput more than twice as high
“Banaman's capex is 20% higher for a plant throughput that's more than twice as high uh twice as large.”
Phil Hoskins· 26 Mar 2026·
npv
could do 3.9 million pounds per annum at 12 year for 12 years
“what we have in our back pocket sort of properly reimagined as I said um could do 3.9 million pounds per annum at 12 year for 12 years”
Phil Hoskins· 26 Mar 2026·
operating cost
20 kilograms of acid per ton of ore treated
“an extremely low acid consumption of 20 kilograms per ton of ore treated.”
Phil Hoskins· 26 Mar 2026·
price assumption
$90 a pound
“the economics at $90 a pound didn't quite stack up”
Phil Hoskins· 26 Mar 2026·
price assumption
$90 a pound
“at $90 a pound um it was roughly NPV equals capex”
Phil Hoskins· 22 Feb 2026·

Financing 8

Key takeaway. Management has provided several cash positions over recent months.

Read the full summary

The company reports having $19 million Australian in the bank at end of December (stated in both March and April 2026), then "just shy of 18 million Australian dollars" at end of March 2026. Looking ahead, management says cash position will be $9 million in the bank by end of year (May 2026). On capital needs, management said in February 2026 that $20 million Australian was needed in Q4 2024, and noted in March 2026 that the company loaned $700,000 to GobX to drill low hanging fruit while a transaction concludes. Regarding burn rate, management stated in April 2026 that $700,000 of drilling delivered a 24% resource increase, and separately mentioned in February 2026 that burn rate was "just short of half by end of calendar year."

What was actually said
cash position
$9 million in the bank by end of year
“our budget has us closing the year with with $9 million in the bank even with 50,000 mters of drilling”
Phil Hoskins· 18 May 2026·
burn rate
700,000 dollars of drilling for 24% resource increase
“To do that with 700,000 dollars of drilling.”
Phil Hoskins· 03 Apr 2026·
cash position
19 million Australian dollars end of December
“Your treasury still around 19 million Australian dollars? Yeah, it was 19 end of December.”
Phil Hoskins· 03 Apr 2026·
Show the other 5 statements
cash position
just shy of 18 million Australian dollars end of March
“Um I think it might be just shy of 18 end of March.”
Phil Hoskins· 03 Apr 2026·
capital needed
loaned $700,000 to GobX to drill low hanging fruit while transaction concluding
“We uh loaned $700,000 to GobX uh to drill what we considered lowhanging fruit while the transaction was concluding”
Phil Hoskins· 26 Mar 2026·
cash position
19 million in the bank end of December
“with 19 million in the bank uh end of December.”
Phil Hoskins· 26 Mar 2026·
burn rate
just short of half by end of calendar year
“I'd say by the end of this calendar year we'll have uh just short of half of that”
Phil Hoskins· 22 Feb 2026·
capital needed
20 million Australian dollars in Q4 2024
“So, you were capitalized in Q4 of last year with 20 million Australian dollars”
Phil Hoskins· 22 Feb 2026·

Timeline 19 statements

Timeline 18

Key takeaway. Management outlined an aggressive timeline for Atomic Eagle in 2026 and 2027.

Read the full summary

The company, listed in November 2025, had a 30,000 m exploration program underway by May 2026—described as the largest the project has seen in almost 20 years—with drilling expected to total upwards of 50,000 meters by year-end and the 30,000 m phase to conclude by August. On the study front, management said a feasibility study update would come in 2027, with 2027 focused on metallurgical test work and updating studies, while a mineral resource update was targeted by end of 2026. First production was guided for towards the end of this decade.

What was actually said
milestone
30,000 m exploration program underway, largest program the project has seen in almost 20 years
“Largest program the project's seen in almost 20 years uh funded to do it.”
Phil Hoskins· 31 May 2026·
milestone
first 13 or 14 drill holes at Chisabuka almost all hit mineralization where expected
“the first 13 or 14 drill holes from the program um almost all of them have hit mineralization where we expected”
Phil Hoskins· 31 May 2026·
study due
2027 will be about met test work and updating studies
“2027 will be about met test work and and updating studies.”
Phil Hoskins· 31 May 2026·
Show the other 15 statements
first production
towards the end of this decade
“reactors are going to be uh dependent on new supply coming out of the ground”
Phil Hoskins· 18 May 2026·
milestone
feasibility study update in 2027
“Then we'll flow into 2027 uh with an update to the feasibility studies”
Phil Hoskins· 18 May 2026·
milestone
Atomic Eagle listed in November 2025
“we listed in November 2025”
Phil Hoskins· 18 May 2026·
milestone
mineral resource update by end of 2026
“updating the mineral resource by the end of the year”
Phil Hoskins· 18 May 2026·
milestone
30,000 meter drill program to be concluded by August
“we're kicking off with a 30,000 meter drill program that will be concluded by August”
Phil Hoskins· 18 May 2026·
milestone
upwards of 50,000 meters drilled by end of year
“it'll end up being upwards of 50,000 meters that we would have drilled by the end of the year”
Phil Hoskins· 18 May 2026·
milestone
2026 field season collection of assay data once mineralization understood
“towards the end of the 2026 field season once we've understood uh where the mineralization is is where we'll bring in the RC and diamond.”
Phil Hoskins· 03 Apr 2026·
milestone
announcement of targets coming out in coming week or two
“the number of targets and the target areas, there will be an announcement coming out in in the coming week or or two”
Phil Hoskins· 03 Apr 2026·
milestone
12 year mine life at 2.2 million per annum from feasibility study 12 months ago
“at 12 months ago there was a NI43101 feasibility study done over the asset um 12 year mine life at 2.2 million peranom.”
Phil Hoskins· 26 Mar 2026·
milestone
first cab off the rank will be drilling rest of Chisabuka that hasn't been drilled, targets through 2026 are new targets with coincident soils and geophysical signatures similar to other deposits
“the first cab off the rank will be drilling the rest of Chisabuka that hasn't been drilled. So, that's infill. Um, and that's um yeah, very likely to add add pounds. Um, the majority of the other targets through 2026 um uh are are new targets.”
Phil Hoskins· 26 Mar 2026·
milestone
drill program starting at beginning of April will be largest program at project since 2007
“the drill program starting at the beginning of April will be the largest program at the project since 2007.”
Phil Hoskins· 26 Mar 2026·
permit timing
environmental approvals and relocation action plan lodged through 2025, will receive approvals this year
“we do uh benefit from the fact that environmental approvals and relocation action plan were all lodged through 2025 in aid of development. So we will receive those approvals this year.”
Phil Hoskins· 26 Mar 2026·
study due
updated feasibility study likely not to commence until 2027
“um essentially go into an updated feasibility study um that would likely not commence until 2027.”
Phil Hoskins· 26 Mar 2026·
milestone
permit approval expected first half of 2025
“environmental social impact assessments and relocation action plans that were previously submitted that we also expect will get approved in the first half of this year”
Phil Hoskins· 22 Feb 2026·
study due
early March 2025
“over the next couple of weeks I think in early March we'll come out with the resource upgrade”
Phil Hoskins· 22 Feb 2026·

Catalysts 1

What was actually said
upcoming result
first results from drilling program announced today
“But um furthermore across montanga north, namac 1 and namac 2. And it's really exciting”
Phil Hoskins· 18 May 2026·

Corporate 7 statements

Management 4

Key takeaway. Management emphasises the team's track record in uranium.

Read the full summary

The company states it was founded by Grant Davyy and Keith Ba, who were the founders of Boss Energy and Lotus Resources, both now uranium producers (May 2026, Mar 2026). Additionally, management notes that COO Warren King was the executive who restarted KA, and consulting geologist Harry Mustard was involved at Lethane uranium and Lotus (Mar 2026). The names appear with slightly different spellings depending on the date of the statement (Davyy vs Davey, Ba vs Bowes).

What was actually said
track record
Founded by Grant Davyy and Keith Ba, founders of Boss Energy and Lotus Resources
“company that was founded by Grant Davyy and Keith Ba, who were founders of Boss Energy and Lotus Resources”
Phil Hoskins· 18 May 2026·
team experience
COO Warren King was executive that restarted KA, consulting geologist Harry Mustard involved at Lethane uranium and Lotus
“chief operating officer for Atomic Eagle is Warren King who was the exec that restarted KA. Um so there's a fair bit of uranium expertise in the group. Our sales and marketing consultant is Chris Lewis who uh exchamico sales and um and our geologist ch consulting geologist Harry mustard was involved at lethane uh uranium and and lotus as well.”
Phil Hoskins· 26 Mar 2026·
track record
Keith Ba and Grant Davyy were founders behind Boss Energy and Lotus Resources which are both now uranium producers
“those two were the founders behind Boss Energy um and Lotus Resources which are both now uranium producers.”
Phil Hoskins· 26 Mar 2026·
Show the other 1 statement
track record
Grant Davey and Keith Bowes involved with Boss Energy (formerly Boss Resources), Lotus Resources/Kayelekera restart
“It first started with Boss, uh was called Boss Resources, now Boss Energy and Matador uh acquired the Kayelekera uranium mine”
Phil Hoskins· 22 Feb 2026·

Share structure 1

What was actually said
shares outstanding
trades under ticker AUXF in United States on OTCQB and AEU in Australia
“Atomic Eagle trades in Australia and also in the United States on the OTCQB under the ticker AUXF and in Australia under AEU.”
Phil Hoskins· 31 May 2026·

Market 2

Key takeaway. Management of Atomic Eagle says its grades are slightly higher on average than those of Deep Yellow, placing the project favourably on the cost curve.

Read the full summary

The company also reports a production target of 4 to 5 million pounds.

What was actually said
cost curve position
grades slightly higher on average than Deep Yellow
“Our grades are slightly higher on average so far.”
Phil Hoskins· 26 Mar 2026·
production target
4 to 5 million pounds
“we could be producing 4 to 5 million pounds um uh via very simple heat leach operations”
Phil Hoskins· 22 Feb 2026·

Sources 5 interviews

Every interview 5

DateChannelInterviewStatements
31 May 2026 MiningStockEducation.com "We're Testing Several High Priority Targets": 30,000m Exploration - Atomic Eagle CEO Phil Hoskins 13
18 May 2026 Crux Investor Atomic Eagle (ASX:AEU) - Pitch Perfect - May 2026 19
03 Apr 2026 MiningStockEducation.com “A Great Stepping Stone”: 24% Resource Increase at Muntanga Project - Atomic Eagle CEO Phil Hoskins 17
26 Mar 2026 Crux Investor Atomic Eagle (ASX:AEU) - Scaling Proven Zambian Uranium Asset Toward Production 27
22 Feb 2026 MiningStockEducation.com “Mega Uranium Mine Concept” via Rapid Resource Growth explained by Atomic Eagle CEO Phil Hoskins 16

What else those interviews covered

Every other asset named in the same recordings, by how many of them named it — the company's coverage context, not its holdings. Where the name is another company we hold a record for, it links to it.

deep yellow 3
bannerman 2
walvis bay 2
mantunga uranium project 2
chissibuka 1
chisibuka 1
global x etf 1
chisabuka 1

Questions people ask

What is Atomic Eagle's project and where is it?

Atomic Eagle is a developer uranium company, with a project stated to be in Zambia. Everything here is drawn from its executives' own interviews.

Which interviews mention Atomic Eagle?

We track 5 interviews mentioning Atomic Eagle, across 2 channels (Crux Investor, MiningStockEducation.com).

What are investors saying about Atomic Eagle?

No independent commentary is on record yet — so far the page carries only the company's own voice.

What do recent interviews with Atomic Eagle cover?

The most-discussed topics on record are the deposit, timeline, economics, jurisdiction — each claim quoted and dated in the sections above.

How to read this page

What is here

Statements made by company representatives in the interviews listed above — each one carrying the words that made it, the date, and the recording. Nothing is added from any other source: if it was not said on a recording, it is not on this page. The one exception lives in the Claims & Checks record, which cites a metal price from our own feed so a stated cost can be set against it — and labels it as ours wherever it appears.

What is not verified

All of it. Resource figures, economics, timelines and promotional framing are management's own representations, checked against no filing and no technical report. Transcripts are automatic; we repair a clearly mis-heard word but never a number, a date, a unit or a speaker's hedge — “about 8.6 million ounces” keeps its “about”.

How to use it

Treat it as a map of what has been said, not as a source of fact. Where a figure matters to you, open the recording and read the company's filings. Nothing here is financial advice, a recommendation, or an offer to buy or sell any security — these are interested parties discussing their own company.

Workspace Intelligence
YOUR AGENT
Investigation
Open the latest investigation, or start a new one from the left.

Notice

Loading…