← Back to TranscriptAgent TranscriptAgent
← All mining companies

Gold Terra ResourcesTSXV:YGT

Gold developer, with a project stated to be in Yellow Knife.

developer gold
Sep 2025 → Jan 2026Covered
9 of 10Topics on record
3Figures tracked over time
1 executiveNamed on the record
Generate Claims & Checks What management and commentators said, and what still needs independent verification 2 interviews with the company
Stage
Developer
Primary commodity
Gold
Jurisdiction
Yellow Knife
Latest appearance
13 Jan 2026
On record
2 interviews · 30 statements · 1 executive

At a glance

What the record holds today. Every card names where it came from — a management representation is not an established fact, and the page never blurs the two.

What is in the ground
14 million ounces of gold produced between 14 to 22 grams
Management-stated Gerald Panneton Jan 2026
Grade
500,000 ounces at 6 g; 700 ounces at six gram; half a million ounces at five grams
Management-stated Gerald Panneton Jan 2026
Money on hand
$3 million in the bank
Stated capital need: need a new mill and new tailings facility
Management-stated Gerald Panneton Sep 2025
What happens next
could be in production before 2029, 2030
Management-stated Gerald Panneton Jan 2026
The main open question
The capital required—a new mill and tailings facility—is substantial and not yet quantified in the material provided.
Weighed from the statements below, not our opinion of the company.
Our reading

How the stated figures have moved

The same figure, as management put it on the earliest and the latest recording we hold. A difference may be a genuine update, a different measure of the same thing (total against indicated), or a mis-heard number — both quotes are here, and both recordings are one click away.

Grade ≠ Different measure Stated in grade, then in ounces — not the same quantity 2 statements on record
29 Sep 2025
3.5 g cutoff grade for underground mining in 2022 September resource
“The current cutoff grid reviews for underground mining is 3.5 g in the 2022 September resource.”
13 Jan 2026
500,000 ounces at 6 g; 700 ounces at six gram; half a million ounces at five grams
“we have a zone of 500,000 ounces plus at 6 g”
Resource size roughly 1.8 million oz500,000 oz ≠ Different basis One statement qualifies the figure and the other does not (combined, indicated, inferred) 7 statements on record
29 Sep 2025
roughly 1.8 million ounces combined resource of indicated and inferred
“We've already outlined we have already outlined roughly 1.8 million ounces combined resource of indicated and infer on our project”
13 Jan 2026
500,000 ounces plus at 6 g
“we have a zone of 500,000 ounces plus at 6 g which did not make the cutoff grade”
Permitting ? Wording changed No comparable date in one of the two statements 2 statements on record
29 Sep 2025
mining lease and surface rights in place
“The carmine is an asset that is very important to the company because it has a mining lease surface rights which is a shortcut towards putting m back the mine into production.”
13 Jan 2026
mining lease and surface rights
“the coal mine has a mining lease and surface rights.”

Management view vs outside view

Management interviews are promotional by nature; the outside view is the counterweight. Both are quoted from the recordings, not added by us.

What management spends its time on

Counted from Gold Terra Resources's own claims across 2 interviews — most-covered theme first.

What outside voices pick up on

No independent commentary on record yet — so far the page carries only the company's own voice.

Bull · Bear · Watch next

Weighed from the statements on this page — management's pitch and the outside view. Not financial advice, and not our opinion of the company.

▲ Bull case

Management says the Campbell shear has demonstrated 14 million ounces of past production at high grades and remains open 600–700 meters below the old mine, with 1.8 million ounces now outlined and a near-surface startup zone of 540,000…

What it rests on
Evidence: 4 moments from 2 interviews
Read the full case

Management says the Campbell shear has demonstrated 14 million ounces of past production at high grades and remains open 600–700 meters below the old mine, with 1.8 million ounces now outlined and a near-surface startup zone of 540,000 ounces already defined. At $2,000 per ounce or higher, 1 million ounces is sufficient to restart production, and the company holds mining leases, surface rights, and the support of O royalty investors.

▼ Bear case

The capital required—a new mill and tailings facility—is substantial and not yet quantified in the material provided.

What it rests on
Evidence: 2 moments from 2 interviews
Read the full case

The capital required—a new mill and tailings facility—is substantial and not yet quantified in the material provided. The company has only $3 million in cash against a stated need for major infrastructure, and financing beyond O royalty's $2 million commitment is unspecified. No independent technical review is on record, and the timeline to production (2029–2030) assumes successful acquisition and permitting before end of 2027.

◆ Watch next

Resource update and preliminary economic assessment due within 6–12 months; acquisition of the Con mine targeted before end of 2027; first production targeted for 2029–2030.

What it rests on
Evidence: 2 moments from 2 interviews
Read the full case

Resource update and preliminary economic assessment due within 6–12 months; acquisition of the Con mine targeted before end of 2027; first production targeted for 2029–2030. Proof of funding for mill and tailings facility and confirmation of resource grade and continuity at depth will determine feasibility.

Each moment links to the exact point in the source recording. The cases are drawn from the transcripts, weighed as written — they are not a rating, a target or a recommendation.

Project 16 statements

The deposit 10

Key takeaway. In a January 2026 interview, management described the deposit as having produced 14 million ounces of gold at grades between 14 and 22 grams historically.

Read the full summary

They reported a current combined resource of roughly 1.8 million ounces (indicated and inferred, based on a September 2025 statement), adding that they see "probably more than two million ounces on the Con mine" and a separate near-surface resource of 540,000 ounces between 200 and 500 metres vertical depth in the Yellow Rex area. Management noted exploration upside across 70 kilometres of the plumbing system. Grade figures vary across the claims: the company referenced a 3.5 g/t cutoff used in the September 2022 resource, and separately cited 500,000 ounces at five grams, 500,000 ounces at 6 g, and 700 ounces at six grams—though the last figure appears to be a likely misstatement of a tonnage or grade target.

What was actually said
exploration upside
covering 70 kilometers of the plumbing system
“Gold terra has access to an excellent excellent portfolio package of exploration uh property covering 70 kilometers of the plumbing system”
Gerald Panneton· 13 Jan 2026·
grade
500,000 ounces at 6 g; 700 ounces at six gram; half a million ounces at five grams
“we have a zone of 500,000 ounces plus at 6 g”
Gerald Panneton· 13 Jan 2026·
resource size
14 million ounces of gold produced between 14 to 22 grams
“Campbell shear where 14 million ounces of gold was produced between 14 to 22 grams.”
Gerald Panneton· 13 Jan 2026·
Show the other 7 statements
resource size
probably more than two million ounces on the con mine
“We have probably more than two million ounces on the con mine.”
Gerald Panneton· 13 Jan 2026·
resource size
a million ounces between surface and a thousand meters
“we can focus on building a mill based on 1 million ounces between surface and 1,000 meters”
Gerald Panneton· 13 Jan 2026·
resource size
another half a million ounces at five grams
“zone 103 which is the northern extension of the Campbell shear that was never mined but was drilled and partly developed back in the 90s on 25 m spacing there's another half a million ounces at five grams”
Gerald Panneton· 13 Jan 2026·
resource size
500,000 ounces plus at 6 g
“we have a zone of 500,000 ounces plus at 6 g which did not make the cutoff grade”
Gerald Panneton· 13 Jan 2026·
grade
3.5 g cutoff grade for underground mining in 2022 September resource
“The current cutoff grid reviews for underground mining is 3.5 g in the 2022 September resource.”
Gerald Panneton· 29 Sep 2025·
resource size
roughly 1.8 million ounces combined resource of indicated and inferred
“We've already outlined we have already outlined roughly 1.8 million ounces combined resource of indicated and infer on our project”
Gerald Panneton· 29 Sep 2025·
resource size
540,000 ounces near surface between 200 m vertical and 500 m vertical in Yellow Rex area
“We already found 540,000 answers near surface between 200 m vertical and 500 m vertical. So we already have the startup of the mine with that yellow Rex area”
Gerald Panneton· 29 Sep 2025·

Jurisdiction 4

Key takeaway. Management of Gold Terra Resources highlights that its project is located in Yellowknife, Northwest Territory (Sep 2025).

Read the full summary

The company reports that both a mining lease and surface rights are in place (Sep 2025, Jan 2026).

What was actually said
permit status
mining lease and surface rights
“the coal mine has a mining lease and surface rights.”
Gerald Panneton· 13 Jan 2026·
country
Northwest Territory
“We are actively uh drilling or preparing for drilling I should say on our project in the Northwest Territory mainly uh concentrated in the town of Yellow Knife.”
Gerald Panneton· 29 Sep 2025·
permit status
mining lease and surface rights in place
“The carmine is an asset that is very important to the company because it has a mining lease surface rights which is a shortcut towards putting m back the mine into production.”
Gerald Panneton· 29 Sep 2025·
Show the other 1 statement
region
Yellow Knife
“We are actively uh drilling or preparing for drilling I should say on our project in the Northwest Territory mainly uh concentrated in the town of Yellow Knife.”
Gerald Panneton· 29 Sep 2025·

Technical risk 2

Key takeaway. Gold Terra Resources management acknowledges that a key assumption—the continuation of the Campbell Shear 600 meters below the mine (stated September 2025)—is a technical risk they test.

Read the full summary

They report that a deep drilling program subsequently proved the shear was open 700 meters below the mine (stated January 2026).

What was actually said
stated risk
deep program proved Campbell shear was open 700 meters below the mine
“we demonstrated that the Campbell shear was open all the way to about 700 meters below the mine”
Gerald Panneton· 13 Jan 2026·
key assumption
continuation of Campbell shear 600 m below the mine
“Most recently we completed a deep program that basically was very successful by technically outlining the the continuation of a Campbell shear 600 m below the mine.”
Gerald Panneton· 29 Sep 2025·

Economics 5 statements

Economics 1

What was actually said
key assumption
1 million ounces is good enough to restart the mine
“we believe that a million ounces at 67 gram is plenty to restart the mine.”
Gerald Panneton· 13 Jan 2026·

Financing 4

Key takeaway. Management of Gold Terra Resources said that as of September 2025 the company had $3 million in the bank and a royalty investor, O royalty, had invested $2 million, with the potential for a further $2 million to increase the royalty to 3%.

Read the full summary

The company noted in January 2026 that it will need a new mill and new tailings facility.

What was actually said
capital needed
need a new mill and new tailings facility
“It's a new mill. Okay. In the new tailings facility which will be on top of the old one but still you still need to build it.”
Gerald Panneton· 13 Jan 2026·
cash position
$3 million in the bank
“we also have $3 million in the bank.”
Gerald Panneton· 29 Sep 2025·
financing status
endorsement from O royalty with potential for further investment of $2 million to increase royalty to 3%
“If they want to go to 3%, they have to write another check for two million, which is again a second endorsement.”
Gerald Panneton· 29 Sep 2025·
Show the other 1 statement
financing status
O royalty invested $2 million
“you've obviously had a Cisco's 2 million bucks in here”
Gerald Panneton· 29 Sep 2025·

Timeline 3 statements

Timeline 3

Key takeaway. Gold Terra Resources management outlined a three-part timeline.

Read the full summary

First, a resource update and preliminary economic assessment (PEA) are due in six to twelve months, as of September 2025. Second, the company aims to complete a deal to purchase the Cam Mine before the end of 2027. Third, management said the project could be in production before 2029 or 2030, based on their January 2026 statements.

What was actually said
first production
could be in production before 2029, 2030
“we could be in production before 2029, 2030.”
Gerald Panneton· 13 Jan 2026·
milestone
deal to purchase the car mine before the end of 2027
“we have a very good path forward to realize this acquisition before 2027.”
Gerald Panneton· 13 Jan 2026·
study due
resource update and PEA in 6–12 months
“If we succeed in drilling what we need to drill over the next six to 12 months, we'll have an update resources. We'll have a pea right after”
Gerald Panneton· 29 Sep 2025·

Corporate 6 statements

Management 2

Key takeaway. Management of Gold Terra Resources says the team's background is in developing a mine "from A to Zed," and notes they have been involved with the company for the last six years (January 2026).

What was actually said
track record
background is developing mine from A to Zed
“my background is developing mine from A to Zed.”
Gerald Panneton· 13 Jan 2026·
track record
involved with the company for the last six years
“I've been involved with the company for the last six years.”
Gerald Panneton· 13 Jan 2026·

Share structure 1

What was actually said
insider stake
supporters include Eric Sprout, David Arquwell, McKenzie
“whether it's McKenzie, Eric Sprat, David Arwell and others or our royalty as well, they all believe we can deliver”
Gerald Panneton· 13 Jan 2026·

Market 3

Key takeaway. Gold Terra Resources' management discusses market assumptions and cost positioning.

Read the full summary

In January 2026, management stated that at $1,700 an ounce the project would need 1.5 million ounces, but with gold above $3,000 and $4,000 the economics change significantly, and that even at $2,000 an ounce the project remains feasible. Separately, in September 2025, the company reported a 3.5 gram cutoff grade valued at $5,600 per ton, indicating its cost position.

What was actually said
price assumption
at $1,700 an ounce needed 1.5 million ounces; gold above $3,000 and $4,000 changes economics
“Back then we said we need a one and a half million answers on the property to justify building a new mill.”
Gerald Panneton· 13 Jan 2026·
price assumption
if we go back to $2,000 an ounce, it's still feasible
“If we go back to $2,000 an ounce, it's still feasible.”
Gerald Panneton· 13 Jan 2026·
cost curve position
3.5 gram cutoff grade valued at $5,600 cut off grade per ton
“3 and a half gram basically is valued at $5 $600 cut off grade for per ton.”
Gerald Panneton· 29 Sep 2025·

Sources 2 interviews

Every interview 2

DateChannelInterviewStatements
13 Jan 2026 Crux Investor Gold Terra Resources (TSXV:YGT) - Former Producing Mine Plans Production in 2029 18
29 Sep 2025 Crux Investor Gold Terra Resources (TSXV:YGT) - Resource Update & PEA in 6–12 Months Ahead of Newmont Option 12

What else those interviews covered

Every other asset named in the same recordings, by how many of them named it — the company's coverage context, not its holdings. Where the name is another company we hold a record for, it links to it.

barrick gold 1
discovery silver 1
gold 1
gold (spot) 1
gold terra resources corp 1
newmont 1
newmont corporation 1
o royalty / osisko 1

Questions people ask

What is Gold Terra Resources's project and where is it?

Gold Terra Resources is a developer gold company. Everything here is drawn from its executives' own interviews.

Which interviews mention Gold Terra Resources?

We track 2 interviews mentioning Gold Terra Resources, across 1 channel (Crux Investor).

What are investors saying about Gold Terra Resources?

No independent commentary is on record yet — so far the page carries only the company's own voice.

What do recent interviews with Gold Terra Resources cover?

The most-discussed topics on record are the deposit, financing, jurisdiction, timeline — each claim quoted and dated in the sections above.

How to read this page

What is here

Statements made by company representatives in the interviews listed above — each one carrying the words that made it, the date, and the recording. Nothing is added from any other source: if it was not said on a recording, it is not on this page. The one exception lives in the Claims & Checks record, which cites a metal price from our own feed so a stated cost can be set against it — and labels it as ours wherever it appears.

What is not verified

All of it. Resource figures, economics, timelines and promotional framing are management's own representations, checked against no filing and no technical report. Transcripts are automatic; we repair a clearly mis-heard word but never a number, a date, a unit or a speaker's hedge — “about 8.6 million ounces” keeps its “about”.

How to use it

Treat it as a map of what has been said, not as a source of fact. Where a figure matters to you, open the recording and read the company's filings. Nothing here is financial advice, a recommendation, or an offer to buy or sell any security — these are interested parties discussing their own company.

Workspace Intelligence
YOUR AGENT
Investigation
Open the latest investigation, or start a new one from the left.

Notice

Loading…